30 E Oak St, Lebanon, OR
-
Store #:
05369
-
Estimated Completion
March 27, 2021
-
Completed Date
April 27, 2021
-
Status
Completed
April 27, 2021
March 27, 2021
March 26, 2021
March 23, 2021
March 22, 2021
- Finished base coat on entrance. Painted.
March 21, 2021
- We got all the cracks caulked and started base
- Rain moved in so had to stop
March 19, 2021
- We pressure washed right front and back side and took sign down on front right.
- We have almost a week of rain. We are going to try and do what we can in-between rain.
- We finished pressure washing.
- Next is base coat.
March 17, 2021
March 17, 2021
- More images of the issues
March 16, 2021
- Every v groove is cracked. They didn’t pit mesh
- And they didn’t use mesh over the stopping/j channel at bottom of foam